Honeywalk Timeline
The Honeywalk Project
Last Updated: 26 April 2017
-->
-->
ENGR 103-68-10
Spring Term 2017
Last Updated: 26 April 2017
-->
Task
| WEEK | |||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
Course Checkpoints | ||||||||||
Form group | X | |||||||||
Blog check #1 | X | |||||||||
Design Proposal | X | |||||||||
Blog check #2 | X | |||||||||
Final report draft | X | |||||||||
Blog check #3 | X | |||||||||
Final report | X | X | ||||||||
Blog Upates/Revisions | X | X | X | X | X | X | X | X | X | |
Final presentation | X | X | ||||||||
Research | ||||||||||
Research current walkway construction | X | X | ||||||||
Research strengths of recycled plastics | X | X | ||||||||
Research greenspaces in urban settings | X | X | ||||||||
Design | ||||||||||
Design locking mechanism | X | X | X | |||||||
3D designs in AutoCAD | X | X | X | |||||||
Hand drawings of walkway proposal | X | X | X | |||||||
Walkway design proposal in AutoCAD | X | X | X | X | X | |||||
Print 1/6 scale 3D parts | X | |||||||||
Test printed parts in machine shop | X | X | ||||||||
Design revisions and reprint (if neccessary) | X | X | X | |||||||
Retest Printed Parts | X | X | ||||||||
Design revisions and reprint (if neccessary) | X | X | ||||||||
Deliverables | ||||||||||
Final 3D Printed Parts | X | |||||||||
Final Walkway Proposal | X | |||||||||
Final Blog updates | X | X | ||||||||
Final Presentation | X | X |